Our team has conducted extensive research to compile a set of Professional practice MCQs. We encourage you to test your Professional practice knowledge by answering these multiple-choice questions provided below.
Simply scroll down to begin!
A. Agreement
B. Verbal agreement
C. Promise
D. Legally binding agreement or promise to exchange goods or services
A. All contracts
B. Contract for the sale of goods worth more than $500
C. Contract for the sale of services
D. Contract that cannot be completed within one year
A. A document that outlines the timeline and budget for a construction project
B. An agreement between two or more parties to do or not do something
C. A legal document that outlines the duties and responsibilities of each party in a construction project
D. A document outlining the location of a construction project
A. The owner/person who has authority
B. The person who is in charge of a school
C. The main part of something
D. A rule or belief that is a fundamental part of a system of thought
A. A natural force that produces a result
B. A person who buys or sells things for others
C. A person who is sent to do something
D. The one providing services and acts on behalf of the principal
A. The agent must be powerful
B. The agent must be wealthy
C. The agent must be honest and loyal
D. The agent must be connected
A. Clauses that can be changed depending on the situation.
B. Clauses that are always negotiable.
C. Clauses that are not important.
D. Clauses that have specific wordings that should not normally be changed.
A. A third party cannot be used in the performance of a contract.
B. Subcontracting is not allowed in some states.
C. When a party to a contract engages a third party to perform the work in the original contract.
D. The original contract is void if a third party is used.
A. Renter
B. Manufacturer
C. Broker
D. Architect and/or engineer
A. When the owner and developer are different people
B. When the owner develops the property
C. When the developer develops the property
D. When the owner and developer are the same person
A. Design the project according to established codes and guidelines
B. Engineer the project
C. Build the project
D. Project manager
A. To manage construction projects
B. To develope design on simple small projects
C. To oversee the construction process
D. To design large buildings
A. Oversees construction projects
B. Performs stress and capacity calculations
C. Designs bridges
D. Manages a team of engineers
A. The person who supervises a construction project
B. Someone who cleans up construction sites
C. A type of wood used in construction
D. A person who the entire construction project is awarded to
A. Prime contractor or prime
B. Foreman
C. Carpenter
D. Subcontractor
A. Only liable for indirect damage suffered by the owner
B. Not responsible for any damage suffered by the owner
C. Responsible for all acts of the subcontractors
D. Only liable for direct damage suffered by the owner
A. Economic and Operations
B. Event and Operations
C. Energy and Oil
D. Errors and Omissions
A. Constructs the building
B. Designs the building
C. Develops the building
D. Manages the construction
A. Set pricing
B. Contract fees
C. Estimated quantities
D. Unit prices
A. Unit price
B. Estimated quantities
C. Estimated quantities and unit pricing
D. Unit pricing
A. Time and material
B. Cost plus
C. Unit price
D. Lump sum
A. Predetermined fee
B. All costs and a predetermined fee
C. All costs
D. No fee
A. When the cost of the project is low
B. When the scope of services cannot be determined accurately in advance
C. When the risk is low
D. When the client is unwilling to pay more
A. The engineer is paid a specific sum for each job, regardless of how many days it takes.
B. The engineer is paid a specific sum for each day spent on the job.
C. The engineer is paid a specific sum for each day spent on the job, plus expenses.
A. A person who owes allegiance to a lord and receives protection and land in return
B. Someone who takes care of another person's property while they are away
C. The minimum amount paid by the client, usually in total and in advance
D. A person who is hired to do a particular job
A. Variable costs and fees
B. Overhead costs
C. Fixed costs and fees
D. Established target costs and fees
A. A percentage of the total cost of the project, paid at different milestones throughout the project.
B. A percentage of the total cost of the project upfront.
C. A percentage of the final total cost of the project.
D. A set amount of money regardless of the final cost of the project.
A. The supplier's ownership of the property
B. The customer's security interest in the property
C. The customer's ownership of the property
D. The supplier's security interest in the property
A. A construction lien is a type of security interest.
B. A construction lien is a loan that is used to purchase land or property.
C. A construction lien is a legal claim on property that the owner owes to a contractor, subcontractor, or supplier.
D. A construction lien establishes the supplier's security interest in the property.
A. When both parties agree to terminate a contract.
B. When one of the parties violates the terms of a contract.
C. When one of the parties fails to satisfy all of its obligations under a contract.
D. When one of the parties satisfies all of its obligations under a contract.
A. A written contract that is not followed
B. A contract being signed by only one party
C. A breach of contract that is not intentional
D. A contractor walking off a construction job
A. Providing work or materials that are below the agreed upon standard.
B. Providing less than adequate quality of work or materials.
C. Not completing the work or project on time.
D. Not providing work or materials.
A. Victim
B. Defendant
C. Offender
D. Plaintiff
A. The act of fulfilling all the remaining provisions of a contract.
B. A clause in a contract that outlines what will happen if one party does not fulfill their obligations.
C. A type of insurance provision in a contract.
D. The act of causing damage to another party in a contract.
A. Awarded in addition to actual damages
B. Not available in all states
C. Awarded instead of actual damages
D. Not available in federal courts
A. The quality or state of being tardy or dilatory
B. A lack of vigor or determination
C. Action, willful or unwillful, taken without proper care or consideration for safety
D. Apathy or indifference to the minimization of risk to life
A. A civil wrong for which damages may be recovered
B. An intentional wrong
C. A criminal wrong
D. A wrongful act
A. A statement that is false but not intentionally so.
B. A statement that is false and relevant.
C. An intentionally false statement known to be false at the time it is made.
D. A statement that is true but not relevant.
A. When there is an acceptance.
B. When there is an offer.
C. When a will is involved.
D. When a contract is involved.
A. Fraud that is committed by a government employee
B. Fraud for which damages are available
C. Fraud that is not intentional
D. Fraud that is impossible to detect
A. Showing beyond a reasonable doubt
B. Showing beyond a scintilla of evidence
C. Showing beyond a clear and convincing evidence
D. Showing beyond a preponderance of the evidence
A. A civil wrong committed by one person causing damage to another person's property
B. A civil wrong committed by one person.
C. A criminal wrong
D. A civil wrong committed by one person causing damage to another person or person's property.
A. A crime is a wrong against society.
B. A criminal lawsuit is a wrong against society.
C. A criminal lawsuit is a wrong against an individual.
D. A civil tort is a wrong against an individual.
A. The accused
B. The state
C. The victim
D. Society
A. A criminal offense
B. Injury
C. An act
D. A breach of contract
A. Must have been criminal
B. Must have been intentional
C. Must have been on purpose
D. Must have been injury
A. Awarded for the direct financial loss due to the breach of contract
B. A formal agreement
C. A written contract
D. Something of value given in exchange for something else
A. To make up for the injury that was sustained
B. To act as a deterrent to future negligence
C. To punish the at-fault party
D. To ease the financial burden of the court case
A. They are all design professionals.
B. They all work with buildings.
C. They all work with structural engineering.
D. They are all architects.
A. Architects, structural engineers, building designers
B. Building designers, structural engineers, architects
C. Structural engineers, architects, building designers
D. Building designers, architects, structural engineers