Managing Project Resources MCQs

Managing Project Resources MCQs

Our experts have gathered these Managing Project Resources MCQs through research, and we hope that you will be able to see how much knowledge base you have for the subject of Managing Project Resources by answering these multiple-choice questions.
Get started now by scrolling down!

1: Capacity-Constrained Resources are the resources that have a limit on the total resource consumption over the life of the project.

A.   True

B.   False

2: Critical Chain is a critical path of a project when resource constraints are considered as well as technological constraints in a project’s precedence network.

A.   True

B.   False

3: ______________ are the resources that have limits on both the utilization rates and total consumption.

A.   Dynamic Task Ordering (Parallel)

B.   Feeding Buffer

C.   Doubly Constrained Resources

D.   Milestone Buffer

4: Dynamic Task Ordering (Parallel) is the ranking of the tasks and changing this ranking during the scheduling process.

A.   True

B.   False

5: A buffer placed between a noncritical task and a critical task in the critical chain methodology is called _____________ .

A.   Dynamic Task Ordering (Parallel)

B.   Feeding Buffer

C.   Doubly Constrained Resources

D.   Milestone Buffer

6: Milestone Buffer is a term used in the critical chain methodology that refers to a buffer that is placed just prior to a milestone (similar to a project buffer).

A.   True

B.   False

7: A hypothesis that work expands to fill the time available for its completion is known as:

A.   Project Buffer

B.   Resource Buffer

C.   Parkinson’s Law

D.   Resource Profiles

8: Project buffer is a buffer placed just before the End milestone to protect the schedule and improve the probability of meeting the due date.

A.   True

B.   False

9: ____________ are the resources that have a limit on the rate at which these resources can be used (e.g., number of workers per day).

A.   Resource Buffer

B.   Rate-Constrained Resources

C.   Resource Profiles

D.   None of these

10: Resource buffer is a buffer placed before a task on the critical chain that uses a new resource type also known as :

A.   Resource Buffer

B.   Rate-Constrained Resources

C.   Resource contention buffer

D.   Resource Profiles

11: Skyline profiles means Frequency histograms showing resource usage per time period.

A.   True

B.   False

12: Single pass are the algorithm that schedules one task at a time and continues until all tasks have been scheduled.

A.   True

B.   False