1: A planned cost contingency used to protect the project budget against the impact of unplanned tasks and task overruns is called ____________.

A.   Expected Critical Path (ECP)

B.   Cost/Work Buffer

C.   Monte Carlo Simulation

D.   PERT

2: The longest path in a project’s precedence network when task expected durations is known :

A.   Expected Critical Path (ECP)

B.   Cost/Work Buffer

C.   Monte Carlo Simulation

D.   PERT

3: ______________ is a process that repeatedly sets values for each random variable by sampling (with replacement) from each variable’s respective distribution.

A.   Expected Critical Path (ECP)

B.   Cost/Work Buffer

C.   Monte Carlo Simulation

D.   PERT

4: An acronym for program evaluation and review technique (may also be project evaluation and review technique) is known as:

A.   Expected Critical Path (ECP)

B.   Cost/Work Buffer

C.   Monte Carlo Simulation

D.   PERT

5: Proactive schedule is a baseline schedule developed during the planning phase in such a way as to protect against schedule disruptions is called _________.

A.   Robust Scheduling

B.   Proactive Schedule

C.   Reactive Schedule

D.   None of these

6: Reactive schedule means no explicit schedule is used; the project tasks simply proceed at a predefined rate.

A.   True

B.   False

7: ________________ is the concept of inserting time buffers into a schedule to develop stable proactive schedules that can withstand some risks.

A.   Proactive Schedule

B.   Robust Scheduling

C.   Reactive Schedule

D.   None of these