Detailed Scheduling in Management MCQs

Detailed Scheduling in Management MCQs

Try to answer these 30 Detailed Scheduling in Management MCQs and check your understanding of the Detailed Scheduling in Management subject.
Scroll down and let's begin!

1: ______ is a scheduling system for service organizations that minimizes customer or client waiting time while maximizing the labor and capacity utilization of the service system

A.   Open loop MRP system

B.   Manufacturing resource planning

C.   Appointment systems

D.   Both b & c

2: Which method who applied to situations in which various resources must be allocated to activities on a one-to-one basis

A.   Open loop MRP method

B.   Manufacturing resource method

C.   Appointment systems

D.   Assignment method

3: Backward scheduling is used to determine in advance the capacity required at each work center for each time period to complete the jobs by the due dates

A.   True

B.   False

4: The critical ratio is a process scheduling that specifies an index number that can be calculated for all jobs

A.   True

B.   False

5: A planning and scheduling method that assumes that within any manufacturing system is known as

A.   Drum-buffer-rope

B.   Open loop MRP planning

C.   Manufacturing resource planning

D.   Appointment systems

6: Define earliest due date .

A.   A priority rule that ranks jobs according to their due dates, and the job that has the earliest due date is processed first and completed

B.   Computerized short-term scheduling that allows the scheduler to make instantaneous changes to the schedule

C.   Computerized short-term scheduling that allows the scheduler to make instantaneous changes to the schedule

D.   All of these

7: Finite capacity scheduling computerized ______ that allows the scheduler to make instantaneous changes to the schedule

A.   Short-term scheduling

B.   Long-term scheduling

C.   Large-term scheduling

D.   All of these

8: A priority rule that specifies the job that arrived first at a work center or machine will be processed first and completed is known as

A.   Last come, first served

B.   First come, first served

C.   Both a & b

D.   None of these

9: _______ is a process scheduling in which many scheduling decisions are predetermined when the production systems were designed

A.   Flow-shop scheduling

B.   Forward scheduling

C.   Finite capacity scheduling

D.   None of these

10: Forward scheduling used to determine the approximate completion time for each job and the capacity required in each time period

A.   True

B.   False

11: Regulating inputs to a work center in relation to output and available capacity Is known as

A.   Input–output control

B.   Job flow time

C.   Forward scheduling

D.   Finite capacity scheduling

12: Job flow time is the total length of time that a job spends at a work center or shop from the point of arrival to the point at which the job leaves the work center or shop

A.   True

B.   False

13: Which method used for sequencing N jobs through two machines, processes, or work centers in the same order to minimize makespan

A.   Johnson’s rule

B.   Job flow time method

C.   Forward scheduling method

D.   Finite capacity scheduling method

14: A priority rule that ranks jobs according to their processing times and the job with the longest processing time will be processed first and completed is known as

A.   Johnson’s rule

B.   Job flow time method

C.   Longest processing time

D.   Finite capacity scheduling method

15: ______ is the total time needed to complete a group of jobs starting with the first job until the completion of the last job

A.   Makespan

B.   Priority rules

C.   Process batch

D.   None of these

16: Priority rules is a simple decision rules that are used to select jobs for the _______ to control the flow of work as jobs

A.   Current operation

B.   During operation

C.   Next operation

D.   All of these

17: Process batch is the lot-size quantity of a product processed at a work center

A.   True

B.   False

18: Reservation systems that uses computerized systems to ______ satisfaction by smoothing out demand for their services in any given time

A.   Maximize customer

B.   Meninize customer

C.   Few customer

D.   Both a & b

19: Which calculations are used to determine a schedule that allocates the capacity of the line among the several products ?

A.   Runout time

B.   Priority rules

C.   Process batch

D.   None of these

20: ______ is the process of determining the exact order or priority of job processing

A.   Sequencing

B.   Shortest processing time

C.   Supply chain scheduling

D.   None of these

21: A priority rule that ranks jobs according to their processing times and the job with the shortest processing time will be processed first and completed is known as

A.   Shortest processing time

B.   Sequencing

C.   Supply chain scheduling

D.   Theory of constraints

22: ______ is the process of coordinating scheduling decisions made by any member of a supply chain with the decisions of other supply chain partners

A.   Shortest processing time

B.   Sequencing

C.   Supply chain scheduling

D.   Theory of constraints

23: Theory of constraints used in a manufacturing process are typically uneven, and to achieve a balanced flow of work through the process

A.   True

B.   False

24: The quantity of units that is transported from one work center to the next is known as

A.   Shortest processing time

B.   Sequencing

C.   Transfer batch

D.   Theory of constraints

25: ______ is the process of coordinating scheduling decisions made by any member of a supply chain with the decisions of other supply chain partners.

A.   Backward scheduling

B.   Forward scheduling

C.   Supply chain scheduling

D.   Flow-shop scheduling

26: Scheduling is complex because setup and ______ and job priorities vary frequently, and machines setup times depend on the order of job processing.

A.   Manufacturing

B.   Production

C.   Master schedule

D.   Processing times

27: ______ is a method for sequencing N jobs through two machines, processes, or work centers in the same order to minimize makespan.

A.   Assignment method

B.   Flow-shop scheduling

C.   Johnson’s rule

D.   Forward scheduling

28: Which of the following refers to calculations that are used to determine a schedule that allocates the capacity of the line among the several products?

A.   Makespan

B.   Longest processing time

C.   Shortest processing time

D.   Runout time

29: ______ is a scheduling system for service organizations that uses computerized systems to maximize customer satisfaction by smoothing out demand for their services in any given time.

A.   Reservation system

B.   Makespan

C.   Finite capacity scheduling

D.   Appointment system

30: ______ is a method applied to situations in which various resources must be allocated to activities on a one-to-one basis.

A.   Assignment method

B.   Flow-shop scheduling

C.   Forward scheduling

D.   Priority scheduling

31: ______ is a form of line process scheduling in which many of the scheduling decisions are predetermined when the production systems were designed.

A.   Backward scheduling

B.   Flow-shop scheduling

C.   Forward scheduling

D.   Supply chain scheduling

32: Which of the following refers to the quantity of units that is transported from one work center to the next?

A.   First come, first served

B.   Makespan

C.   Reservations

D.   Transfer batch

33: ______ involves allocating specific resources such as labor, equipment, and facilities to produce a product or deliver a service.

A.   Manufacturing

B.   Scheduling

C.   Job processing

D.   Sustainability

34: ______ is a computerized short-term scheduling that allows the scheduler to make instantaneous changes to the schedule.

A.   Reservation system

B.   Makespan

C.   Finite capacity scheduling

D.   Appointment system

35: ______ is the total time needed to complete a group of jobs starting with the first job until the completion of the last job.

A.   Makespan

B.   Longest processing time

C.   Shortest processing time

D.   Runout time

36: Which of the following refers to the total length of time a job spends at a work center or shop from the point of arrival to the point at which the job leaves the work center or shop?

A.   Job flow time

B.   Longest processing time

C.   Shortest processing time

D.   Runout time

37: A component of scheduling which is rarely considered is the manner in which ______ plays a part in the scheduling decision.

A.   Production

B.   Quality control

C.   Job processing

D.   Sustainability

38: Manufacturers use different methods for scheduling, depending upon their specific types of ______.

A.   Operations

B.   Products

C.   Services

D.   Master schedule

39: Which priority rule is based upon a calculation of the time remaining between the due date and the time remaining to process the work?

A.   Shortest processing time

B.   Longest processing time

C.   Critical ratio

D.   Earliest due date